Question 441 · 683 in bank
A change advisory board just approved a change request. Which of the following is the MOST likely next step in the change process?
Show answer
Answer: A
Explanation
The change management phases are as follows: Request forms, Purpose of change, Scope of the change, Date and Time of the change, Affective systems/ impact, risk analysis, change board approval, finally end user acceptance. With this the answer is end user acceptance.