The project manager of a large construction project discovers that the blueprints received from the client appear incomplete. What should the project manager do first?
Show answer
Answer: C
Project Management Professional1,401 questions across 141 pages are complete and free, with no account or card.
1401 questions in this bank
Free access · progress saved on this device
The project manager of a large construction project discovers that the blueprints received from the client appear incomplete. What should the project manager do first?
Answer: C
The customer's project manager changes during the final stage of a project. How can the project manager avoid a project closure delay?
Answer: A
The project manager should choose option A: Update the stakeholder engagement plan. When there’s a change in key stakeholders, such as the customer’s project manager, it’s important to update the stakeholder engagement plan. This plan outlines how stakeholders will be engaged and communicated with throughout the project. Updating this plan to reflect the new project manager’s communication preferences, expectations, and level of involvement can help ensure a smooth transition and avoid delays in project closure.
Source: Adapted from community discussion — josephsafiran
A project manager realizes that the team members are new to the hybrid approach and do not value standup meetings. Team members often arrive late, digress into solutioning, or skip the meetings altogether. How should the project manager improve this situation with the project team?
Answer: C
In an industrial plant, the owner has decided to add more capacity to the plant by installing a new machine and updating the software used in production. This capacity enlargement will occur while the plant is still functioning and producing. The software update will be accomplished using an agile approach in order to minimize risk. The machine procurement, installation, and integration will be accomplished using predictive approaches. What types of communications will the project manager have to design into the schedule management plan to ensure the project will be on schedule?
Answer: A
Initially, i also chose B but i turned to A now. The difference between A & B is 'Colocation' which may not be feasible. same as face to face. so it makes A to be the better choice
Source: Adapted from community discussion — aqz_111
An agile team has started a new project. When should the project manager organize their first team retrospective?
Answer: B
During the review of a project's list of deliverables, one of the stakeholders expressed concern that one of the requirements will not be addressed. What should the project manager do?
Answer: C
Suggested answer, Option C, is correct in my opinion. Option A is wrong and a trick I think. Because there isn't "approved list of requirements" in PMBOK. There is only "requirements traceability matrix" in PMBOK. Option B and Option D can be done if option C doesn't solve the issue in question. So I think option C is the first step to do.
Source: Adapted from community discussion — noppy
During the project quality control process, the project manager realizes that the quality management plan does not include how the final user will perceive the benefits of the new product compared with the actual product. What should the project manager do first?
Answer: D
During project execution, a conflict occurs between the project manager and one of the team members at every project team meeting. The ongoing conflict is preventing tasks and deliverables from being completed. The project manager contemplates changing their leadership style. What should the project manager do?
Answer: A
A. Review the set of responsibilities with the team member. In a situation where there is ongoing conflict between the project manager and a team member, it's important to first review and clarify the roles and responsibilities of both parties. This can help identify any misalignment or misunderstandings that may be contributing to the conflict. By having a clear discussion about roles and responsibilities, expectations can be set, and potential sources of conflict can be addressed. It's a proactive step to try to resolve the conflict and improve collaboration within the team. If the conflict persists, further actions may be necessary, but starting with clarification of responsibilities is a good initial approach.
Source: Adapted from community discussion — Only12go
To prevent influential stakeholders from dominating product delivery decisions, the product owner decided to use planning poker. What is a key advantage of using this technique?
Answer: D
While finalizing project management plans, a customer provides the project manager with a new set of quality standards to which the final product must adhere. What should the project manager do to ensure a smooth delivery of the product?
Answer: D
D. Agree with the client on acceptance criteria Explanation: When the customer provides a new set of quality standards that must be met for the final product, it is important for the project manager to ensure a smooth delivery by agreeing with the client on acceptance criteria. Acceptance criteria define the specific conditions and requirements that the final product must meet to be accepted by the client.
Source: Adapted from community discussion — ANAS3796
Keyboard:J Kmove between questionsA–Dselect an answerRshow or hide the answer← →change page
PMP practice, question 991. 1401 questions available.
Version 1.0.0. How we source questions