Question 81 · 204 in bank
Critical deliverables are delayed, because a key subject matter expert (SME) does not have enough time to allocate to the tasks. How could the situation be improved for the future?
Show answer
Answer: A
PMI Risk Management Professional204 questions across 21 pages are complete and free, with no account or card.
204 questions in this bank
Free access · progress saved on this device
Critical deliverables are delayed, because a key subject matter expert (SME) does not have enough time to allocate to the tasks. How could the situation be improved for the future?
Answer: A
A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority. What should the risk manager do?
Answer: B
I would recommend option B: Perform a sensitivity analysis and determine the correct priority of every identified risk. It is important for the risk manager to assess the likelihood and impact of each identified risk in order to prioritize them effectively. Treating every risk as an extremely high priority may not be practical or necessary, and could lead to resource constraints and potential delays in the project. By performing a sensitivity analysis, the risk manager can evaluate the risks and determine which ones need the most attention and resources based on their potential impact on the project. This will allow the risk manager to effectively allocate resources and prioritize risks in a way that is both realistic and effective in mitigating potential risks to the project.
Source: Adapted from community discussion — IBANGA007
An organization that spans across different countries undergoes a digital transformation project. The project manager has assigned a risk management team leader who is a risk management certified candidate in their domain. What should the risk management team leader do in the early stages of the project?
Answer: C
What are the critical success factors for the Plan Risk Management process?
Answer: B
As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will occur is 60% and its monetary impact to the project is US$20,000. What is the total contingency budget that should be created?
Answer: C
What items should be included in a complex project's risk management plan?
Answer: B
A project manager wants to work on understanding the project risks. The project manager works with the integrated project team to develop the risk handling strategies for the identified risks. How should the project manager work with these risk handling strategies?
Answer: A
Which analysis method has a lower standard deviation?
Answer: D
The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of the previous project had to be shut down unexpectedly to wait for the late delivery of the GTG. What should the project manager do first?
Answer: C
A risk manager is confident that they have identified and quantified the risks and opportunities for a project. When presenting their work to management, on what areas should the risk manager focus? (Choose two.)
Answer: AC