Question 101 · 204 in bank
Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted. What will help calculate the impact?
Show answer
Answer: B
Explanation
B. Risk analysis If multiple workstreams are showing issues three months into a program, and the program manager requires that a risk impact assessment be conducted, it is likely that risk analysis will be the most effective approach for calculating the impact of these risks. Risk analysis is a process that helps to understand the likelihood and impact of identified risks, and to determine the appropriate risk response strategies. It involves evaluating the potential consequences of a risk, as well as the likelihood of that risk occurring. This helps to prioritize risks and focus risk management efforts on the most important risks.