Question 51 · 204 in bank
During the execution of a multi-million dollar project, the project manager learns of the theft of important installation materials at one of the most time-critical sites. The project manager contacts the risk manager to discuss further steps, based on the risk register and the defined risk strategy for the risk of theft. However, the risk manager clarifies that the risk of theft was not identified in the risk management process. What should the project manager do next?
Show answer
Answer: A
Explanation
the key is "include the risk of theft in the issue log." we do not include risk of theft to issue log, but to the risk register.