When monitoring the execution quality of risk-related plans and processes, which of the following would be a useful metric to track and record?
Show answer
Answer: B
PMI Risk Management Professional204 questions across 21 pages are complete and free, with no account or card.
204 questions in this bank
Free access · progress saved on this device
When monitoring the execution quality of risk-related plans and processes, which of the following would be a useful metric to track and record?
Answer: B
A project manager identifies a risk in a multifunctional project and decides to take no action. What should the risk manager do if the risk occurs?
Answer: C
The project manager must evaluate two separate contractors for a project with an absolute finish date of 15 December. After performing a Monte Carlo assessment on the submitted schedules, the following information is found:
Which contractor should be chosen, because of having the highest statistical output?
Answer: C
Correct answer C. Multiply the probability and the confidence for each seller then select the higher one (0.50×0.60) 0.3 > 0.26 (0.65x0.40) so select seller A.
Source: Adapted from community discussion — AllPMI
When analyzing the reward system in a company, there is evidence that "fire-fighter behavior" is the highest rewarded behavior. It suggests that people are dealing with major problems primarily in an emergency mode, and deploying quickly. Secondly, those who work efficiently are getting the most attention and recognition for their efforts. What impact does this observation potentially have on the risk management process?
Answer: B
Which of the following techniques for planning risk response can provide a means of identifying symptoms for use as trigger conditions for contingency responses?
Answer: C
What is the purpose of mitigating negative risks as a part of the risk response process?
Answer: B
What best describes the job of a risk owner?
Answer: A
A six-month, USS1.2 million project is two months completed. The project has 3 high, 6 medium, and 2 low risks, with a 10% reserve for known risks, and a 5% reserve for unknown risks. Most of the project's reserves have not been spent. The risk manager, who is also the project schedule manager, establishes monthly risk management reviews to evaluate performance. So far, the project has missed 50% of the planned risk mitigation milestones. Based on this project data, what technique should the risk manager recommend to improve the risk management process?
Answer: C
Which of the following best describes the strength of the probability and impact matrix for qualitative risk analysis?
Answer: B
The risk manager and the project team conduct a risk brainstorming session for a new project. The risk manager wants to involve the entire project team in a group risk prioritization exercise for the identified risks. The project manager refuses the involvement of the entire project team due to resource concerns. What should the risk manager do?
Answer: A
Convince the project manager about the importance of the project team members in all risk management process. Everyone should be involved in the Project Risk Management process "risk management is everyone’s responsibility". It's a key success factor of risk management. The reference is the standard for risk management in portfolios, programs, and projects page#17.
Source: Adapted from community discussion — AllPMI