Question 241 · 341 in bank
An agile team is struggling to achieve their goal during the first release due to an unstable environment beyond the authority of the product owner. Close to the end of the current sprint, the release manager resigns and a new person takes over. What should the scrum master do?
Show answer
Answer: B
Explanation
In Agile, particularly in Scrum, the daily standup (or daily Scrum) is primarily intended for the development team, the Scrum Master, and the Product Owner. The purpose of the daily standup is to provide a quick status update, synchronize the team's efforts, and identify any impediments or blockers. It is a focused, time-boxed meeting that usually lasts around 15 minutes. the arrival of a new release manager can be considered a special circumstance that justifies their temporary attendance at daily standups. This approach ensures a smooth transition, fosters a better understanding of the team’s needs, and facilitates a quicker resolution of any environmental or external challenges affecting the team. However, it’s important to ensure that the standup remains focused and that this is not turned into a long-term practice.
Source: Adapted from community discussion — zayn_1983