Question 41 · 497 in bank
The project manager is using co-location and providing training to the project team. On which of the following Project Resource Management processes is the project manager working?
Show answer
Answer: D
Certified Associate in Project Management497 questions across 50 pages are complete and free, with no account or card.
497 questions in this bank
Free access · progress saved on this device
The project manager is using co-location and providing training to the project team. On which of the following Project Resource Management processes is the project manager working?
Answer: D
In an adaptive or agile life cycle, how are the customer and sponsor involved in the project scope management activities?
Answer: C
C - Overall, the customer and sponsor have a continuous and collaborative involvement in project scope management activities in adaptive or agile life cycles. Their active participation ensures that the project stays aligned with their needs and expectations.
Source: Adapted from community discussion — Amylsmith25
A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?
Answer: B
A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs to make this decision?
Answer: C
Which of the following tasks focuses on decomposing work packages?
Answer: B
The project manager is explaining to others the essential business aspects of the project. To which skill category does this ability belong?
Answer: C
What tool should a project manager use to efficiently manage project resources?
Answer: B
Which process is engaged when a project team member makes a change to project budget with the project manager's approval?
Answer: D
D is answer. The Control Costs process is part of the Project Cost Management knowledge area and is focused on monitoring the status of the project to update project costs and manage changes to the cost baseline. In this process, the project manager reviews the project's actual costs and compares them to the planned costs to identify variances. If a project team member makes a change to the project budget with the project manager's approval, this change would be captured and documented as part of the Control Costs process.
Source: Adapted from community discussion — Hungdv
Which conflict resolution technique produces the most lasting results?
Answer: D
What is the best tool to calculate the critical path on a project?
Answer: D
D-Project Network Diagram is the best choice here, although they may be going for CCM, but that was removed from the current edition
Source: Adapted from community discussion — MoonManBlue
Keyboard:J Kmove between questionsA–Dselect an answerRshow or hide the answer← →change page
CAPM practice, question 41. 497 questions available.
Version 1.0.0. How we source questions