HOTSPOT - You are using Agile process methodologies in Azure DevOps. You need to deploy a dashboard that will provide progress reports for the following work items: • How long it took to close a work item after it was created. • How long it took to close a work item after the work was started. Which type of widget should you use for each work item? To answer, select the appropriate options in the answer area. NOTE: Each correct selection is worth one point.
This is an interactive task on the real exam — a drag-and-drop, hotspot or ordering question. There is nothing to select here, so the answer is shown below for reference.
Show the answer figure
Answer: See figure below
Explanation
1. Lead time 2. Cycle time https://learn.microsoft.com/en-us/azure/devops/report/dashboards/cycle-time-and-lead-time?view=azure-devops Both lead time and cycle time widgets are useful to teams. They both indicate how long it takes for work to flow through their development pipeline. Lead time measures the total time elapsed from the creation of work items to their completion. Cycle time measures the time it takes for your team to complete work items once they begin actively working on them.
Source: Adapted from community discussion — zellck