Question 1141 · 1449 in bank
Which of the following is the PRIMARY objective of providing an aggregated view of IT risk to business management?
Show answer
Answer: D
Explanation
Agree.An aggregated view of IT risk provides a comprehensive and holistic view of the risks that the organization faces. This view consolidates risk information from different sources and provides a high-level summary of the organization's overall risk posture. By providing this aggregated view, business management can obtain consistent data on risk, which is critical for making informed decisions around risk management.