Which of the following techniques would be used during a risk assessment to demonstrate to stakeholders that all known alternatives were evaluated?
Show answer
Answer: D
Explanation
The control chart is a graph used to study how a process changes over time. A Decision Tree Analysis is a graphic representation of various alternative solutions that are available to solve a problem. Hence the correct solution is Decision tree. Happy to hear from other experts.