Which of the following is the BEST course of action when risk is found to be above the acceptable risk appetite?
Show answer
Answer: A
Explanation
Correction, reason: The risk response plan outlines the actions that should be taken when a risk exceeds the acceptable risk level. The response could be to mitigate the risk, transfer the risk, avoid the risk, or accept the risk. The plan should have been developed during the risk management planning phase and should be reviewed periodically to ensure that it remains relevant and effective. Therefore, executing the risk response plan would be the most appropriate action to take in this situation.