A project manager has determined that the critical path of a project is 243 days. However, knowing that the standard deviation is eight days, the project manager would like to provide an estimate to the stakeholders with 95% confidence. Which of the following time frames should the project manager communicate to the stakeholders?
Show answer
Answer: C