Question 421 · 1401 in bank
Select 2A team is testing a product on multiple radio frequencies. The project manager is informed that a new government policy, expected in 2 weeks, will mandate companies to obtain approval and licensing for frequency testing. The team has completed 80% of the testing and needs 4 weeks to complete the remaining tests. Which two actions should the project manager take until the approval is received? (Choose two.)
Show answer
Answer: DE
Explanation
There is no concern highlighted with the current testing team, so hiring a vendor does not add value. C makes sense but pending effort is of 4 weeks but time left is 2 weeks for the possible compliance to come in play. Hence D and E would be the right answer. The new policy is expected in 2 weeks. Why stop testing immediately. So B does not make sense.