Question 151 · 370 in bank
You have an Azure Data Factory pipeline named P1. You need to schedule P1 to run at 10:15 AM, 12:15 PM, 2:15 PM, and 4:15 PM every day. Which frequency and interval should you configure for the scheduled trigger?
Show answer
Answer: B
Explanation
Correct me if I am wrong guys, but if option B is correct does that mean you have to create 4 separate triggers with the Frequency: Day and Interval: 1? If that is the case then I am more inclined to B, since D will still run even after 4:15PM. If we want it to run only for the 4 times specified above then B is a more accurate answer.
Source: Adapted from community discussion — Delphin_8150