Question 651 · 1459 in bank
During a project meeting for the implementation of an enterprise resource planning (ERP). a new requirement is requested by the finance department. Which of the following would BEST indicate to an IS auditor that the resulting risk to the project has been assessed?
Show answer
Answer: B
Explanation
They are referring to the risk to the project - scope creep will always result in additional cost and delay in implementation. This directly translate to the risk to the project, which is what the question asked for
Source: Adapted from community discussion — botherder88