Question 121 · 126 in bank
While discussing the initiative, the team considers cancelling the remaining work. This is an example of the following agile business analysis principle:
Show answer
Answer: B
IIBA Agile Analysis Certification126 questions across 13 pages are complete and free, with no account or card.
126 questions in this bank
Free access · progress saved on this device
While discussing the initiative, the team considers cancelling the remaining work. This is an example of the following agile business analysis principle:
Answer: B
After much discussion the team decides to represent the goal and scope of an initiative with images and words using the following technique:
Answer: B
The sponsor decides to cancel an initiative based on customer feedback. The immediate next step is to:
Answer: D
When facing new competitive threats, getting real using examples at the strategy level, addresses the risk of making poorly defined decisions by:
Answer: C
The delivery team has been busy developing product features and have lost sight of how the individual features align with the overall strategy. They are unsure of progress against the initial product vision. What artifact can they assess to ensure they are aligned:
Answer: B
The team is discussing one of the six key terms used to discuss both business analysis and its relationship with common terminology. Specifically, they are discussing what can cause changes by motivating stakeholders to act. This team is discussing:
Answer: B
Keyboard:J Kmove between questionsA–Dselect an answerRshow or hide the answer← →change page