When can changes to requirements occur in a business analysis planning and monitoring assignment?
Show answer
Answer: B
Certification of Capability in Business Analysis515 questions across 52 pages are complete and free, with no account or card.
515 questions in this bank
Free access · progress saved on this device
When can changes to requirements occur in a business analysis planning and monitoring assignment?
Answer: B
You are the business analyst for your organization. You are coaching Tom about the different approaches to business analysis. Which type of business analysis approach has the most business analysis work at the beginning of the project or during the start of a project phase?
Answer: C
Some of the requirements in the solution must be completed because of laws and regulations in your industry. Management would like you, the business analyst, to rank the requirements according to the relevant laws. What type of requirements prioritization is management having you complete?
Answer: D
There are three inputs for stakeholder analysis. Which input describes the existing organizational units and their interactions with one another?
Answer: B
Which of the following defines all of the features and functions of the thing, solution, or service the project or organization will create?
Answer: D
You are the business analyst for your organization. You're considering if you should make a solution or purchase it from a vendor. If your team creates the solution, it will cost $286,000 and will cost $2,400 per month to support. The vendor's solution, however, will cost $239,000 and will cost $2,850 per month to support. How long will you need to use your in-house solution to be more cost effective than the vendor's proposed solution?
Answer: A
You are the business analyst for your organization and you're notifying the key stakeholders of a need to gather requirements for an endeavor. One of the stakeholders that you'll need to attend your requirements workshop is the project manager. What role will the project manager have in this workshop?
Answer: B
You are a Business Analyst for your organization, and you're preparing to elicit requirements from stakeholders. You've gathered several inputs to help with the elicitation process. Which input will you use to ensure that you understand the type of information that should be elicited from stakeholders?
Answer: C
Nancy has asked you to trace a particular requirement for her. What does 'to trace a requirement' mean?
Answer: D
Which elicitation activity is best described to ensure that the needed resources are organized and available for the elicitation?
Answer: B