Question 21 · 210 in bank
You are building the CI/CD pipeline for an application deployed to Google Kubernetes Engine (GKE). The application is deployed by using a Kubernetes Deployment, Service, and Ingress. The application team asked you to deploy the application by using the blue/green deployment methodology. You need to implement the rollback actions. What should you do?
Show answer
Answer: C
Explanation
The point of using blue/green deployment is to have both blue & green versions deployed, and we chose the active one at service level, so rollback should only consist of updating the service to serve the other version.
Source: Adapted from community discussion — florian_cartron