Question 31 · 53 in bank
Which is a reason for releasing a product into a staging area?
Show answer
Answer: B
PRINCE2 Agile Foundation53 questions across 6 pages are complete and free, with no account or card.
53 questions in this bank
Free access · progress saved on this device
Which is a reason for releasing a product into a staging area?
Answer: B
When tracking progress, which term describes using agile techniques at the delivery level, and traditional techniques at the direction and management levels?
Answer: C
What should be decided when configuring PRINCE2 effectively?
Answer: B
Which two statements are key responsibilities of supplier representative? 1. They highlight areas that the project may impact from a technical perspective. 2. They are partially assigned to the delivery team. 3. They create the project's specialist products. 4. They prioritize requirements.
Answer: A
Which is a purpose of the quality theme?
Answer: A
What is an epic?
Answer: D
Which is an advantage of using the PRINCE2 Agile behavior 'collaboration'?
Answer: D
Which is typically used in agile when estimating detailed requirements during sprint planning?
Answer: D
How does agile address the risk associated with the project not being fully understood at the beginning?
Answer: B
Which TWO statements about the typical tailoring of a checkpoint report in an agile environment are CORRECT? 1. It should be replaced by the project manager attending a daily stand-up. 2. It should be displayed in the form of an information radiator in a team room. 3. It should be produced when the amount to be delivered will result in tolerance being exceeded. 4. It should be produced in a product backlog in the form of prioritized user stories.
Answer: A