Question 891 · 1449 in bank
When reviewing a business continuity plan (BCP), which of the following would be the MOST significant deficiency?
Show answer
Answer: D
Explanation
There is nothing worse than Recovery time objectives (RTOs) that do not meet business requirements. This simply means the BRP is irrelevant and all recovery processes including DRP will be wrong as well. The correct answer is D.
Source: Adapted from community discussion — hussmohsin