When reviewing management's IT control self-assessments, a risk practitioner noted an ineffective control that links to several low residual risk scenarios. What should be the NEXT course of action?
Show answer
Answer: D
Explanation
Answer should be D. The control is ineffective and linked to multiple low risks so there is potential of ineffective control to increase the risk when aggregated. So reevaluation of risk seems like a best fit here.