Question 451 · 1243 in bank
To inform a risk treatment decision, which of the following should the information security manager compare with the organization's risk appetite?
Show answer
Answer: D
Explanation
D. Level of residual risk. When informing a risk treatment decision, the information security manager should compare the level of residual risk with the organization's risk appetite. Residual risk is the risk that remains after risk treatment has been applied. By comparing the level of residual risk to the organization's risk appetite, the information security manager can determine if the risk is acceptable or if additional treatment is required. The organization's risk appetite is a statement of the level of risk that the organization is willing to tolerate and accept. By understanding the residual risk, the information security manager can make informed decisions on risk treatment options and prioritize them accordingly. It is important to note that other factors such as gap analysis results, level of risk treatment and configuration parameters are important to consider, but they don't provide a clear picture of the risk level that the organization is willing to accept.
Source: Adapted from community discussion — Broesweelies