Question 861 · 1459 in bank
An IS auditor notes that the previous year's disaster recovery test was not completed within the scheduled time frame due to insufficient hardware allocated by a third-party vendor. Which of the following provides the BEST evidence that adequate resources are now allocated to successfully recover the systems?
Show answer
Answer: D
Explanation
A service level agreement (SLA) is a contract between an organization and its vendor that outlines the vendor's responsibilities for providing specific services, such as disaster recovery. The SLA should include provisions for the availability of adequate hardware and other resources required to support the disaster recovery process. By reviewing the SLA, the IS auditor can determine whether the vendor has made any changes to their resources allocation or service offerings that would address the issue noted in the previous year's disaster recovery test.