Question 1001 · 1459 in bank
Which of the following should be of GREATEST concern to an IS auditor reviewing project documentation for a client relationship management (CRM) system migration project?
Show answer
Answer: D
Certified Information Systems Auditor1,459 questions across 146 pages are complete and free, with no account or card.
1459 questions in this bank
Free access · progress saved on this device
Which of the following should be of GREATEST concern to an IS auditor reviewing project documentation for a client relationship management (CRM) system migration project?
Answer: D
Which of the following is the MOST important prerequisite for implementing a data loss prevention (DLP) tool?
Answer: A
Which of the following BEST guards against the risk of attack by hackers?
Answer: D
D. Firewalls Firewalls are the best option among the choices provided to guard against the risk of attack by hackers. A firewall is a network security system that monitors and controls incoming and outgoing network traffic based on predetermined security rules.
Source: Adapted from community discussion — Alizade
Which of the following approaches would utilize data analytics to facilitate the testing of a new account creation process?
Answer: B
Which of the following approaches provides the BEST assurance and user confidence when an organization migrates data to a more complex enterprise resource planning (ERP) system?
Answer: B
The answer is B because it allows users to compare the outputs to ensure that the new system performs accurately and reliably before fully transitioning. Parallel processing it allows for immediate verification of data integrity and system functionality, which is crucial in complex ERP environments. I feel the key work here is 'data migration' and not development of the complex ERP system. In the case of development, i would choose C as the best approach would be to implement the system in stages.
Source: Adapted from community discussion — PurpleParrot
During an ongoing audit, management requests a briefing on the findings to date. Which of the following is the IS auditor's BEST course of action?
Answer: D
the client ( Management) pays the auditor for an audit, and wants an update, even during the audit, from the auditor not from the auditee. Also you never say no to a cient if he wants an update at any period of the audit. So D is the answer, just for discussion.. Nothing formal.
Source: Adapted from community discussion — cidigi
Which of the following provides the MOST assurance over the completeness and accuracy of loan application processing with respect to the implementation of a new system?
Answer: A
Which of the following is the PRIMARY concern when negotiating a contract for a hot site?
Answer: B
An IS auditor identifies that a legacy application to be decommissioned in three months cannot meet the security requirements established by the current policy. What is the BEST way for the auditor to address this issue?
Answer: B
Which of the following should be done FIRST when planning a penetration test?
Answer: C
I change my answer to C. According to CRM, chapter 5 page 335, it is imperative to obtain Management’s consent in writing before finalization of the test/ engagement scope. The chosen answer C is correct
Source: Adapted from community discussion — Rachy