Question 21 · 371 in bank
Which of the following is the BEST action to perform before applying patches to one of the hosts in a high availability cluster?
Show answer
Answer: D
Explanation
D. Failover all VMs This ensures that the VMs remain operational and accessible while the host system is being updated, minimizing downtime and maintaining the availability of services. Why? Maintains Service Availability: By failing over VMs to another host, critical services and applications continue to run without interruption. Minimizes Risk: Moving VMs away from the host being patched reduces the risk of service disruption if unexpected issues arise during the patching process. Failing over all VMs to another host within the cluster is a direct and effective way to ensure that services remain available and uninterrupted during the maintenance process, adhering to best practices for managing high availability environments.