Question 61 · 871 in bank
Which of the following would be used to enforce and schedule critical updates with supervisory approval and include backup plans in case of failure?
Show answer
Answer: E
Explanation
"Enforce and schedule critical updates" > this is a massive change to an organization, so the organization is forcing the IT team to schedule the change to let everyone know about the change "Supervisory approval" > someone or a group of people has to approve the change before it can be implemented throughout the organization "Include backup plans in case of failure" > if the change fails, then the IT team has backups to restore data. This was all covered in the CompTIA A+.