Question 581 · 1017 in bank
A company will migrate 10 PB of data to Amazon S3 in 6 weeks. The current data center has a 500 Mbps uplink to the internet. Other on-premises applications share the uplink. The company can use 80% of the internet bandwidth for this one-time migration task. Which solution will meet these requirements?
Show answer
Answer: D
Explanation
7 Years, 5 Months, 3 Weeks, 5 Days required to transfer 10PB on 400 Mbps. Finger cross the upload don't drop or timeout on year 7.
Source: Adapted from community discussion — Cyberkayu